Status of ongoing works at CLW
Click for update | Railway Bord | Home
Sno. Name of Work PB Item no. Sanctioned Cost Expenditure so far Work involved Status Target Last updated
1 6/28/2015
2 Augmentation of production capacity to 200 electric locos per year 11 of 2007-08 Original :66.0 Cr.Revised : 92.51 Cr. Re-revised 92.51 Cr. 71.31 Cr. Addl. bay for shell fabrication. complete March`2017 9/22/2016
Extenstion of traction motor shop complete
Power supply supply augmentation complete
PCMIS
Stores Godown
M&P 90 % complete
Jigs & fixtures complete
3 Modernization of CLW by improving infrastructure and production processes for raising production capacity to manufacture 275 electric locos (200 three phase + 75 conventional locos) per year. 16 (CLW) of 2010-11. 130 Cr. Detailed estimate 134.42 Cr. 25.26 Cr Construction of a new assembly bay Tender document & M&P indent documents under preparation. Dec'2017 9/22/2016
Extension of electric loco assy shop no. 16 & 19. Tender for civil work is being called
Augmentation of traction motor shop. Complete
Modernization of design office.
Improvement in communication.
Laying of additional track In progress
Augmentation of fabrication and bogie shops